Sewer replacement work in Wards Corner

titustown

Titustown Pump Station, Phase 3. Project construction is currently 15% complete. Project includes constructing new sanitary sewer and water mains along Hughart, Wilingham, and Wilmington Streets.

 

titustown4

Titustown Pump Station, Phase 4. Construction to start this winter. Project includes the construction of new sanitary sewer and water mains on Hughart, Matthew Henson, Hannah, and Baltimore Streets.

 

virginian

Virginian Drive 16″ Water Main. Project is still in design phase. Construction to start in Spring 2015. New replacement water main will be installed along Virginian Drive.

 

wardscorner3

Wards Corner Sewer Replacement, Phase 3. Construction along N Shore Road is now 100% complete.

 

wardscorner4

Wards Corner Sewer Replacement, Phase 4. Construction to being this winter. Construction will include new sewer mains along Little Creek, Burleigh, and Maycox.

 

Advertisement

One Response to Sewer replacement work in Wards Corner

  1. pipebursting says:

    Reblogged this on Western States pipebursting and commented:
    If you are a city or contractor that is planning on replacing pipe, please don’t dig a trench. Call Western States Pipebursting, so that we can give you an estimate on a threnchless solution that is a fraction of the cost and much more convenient too.

%d bloggers like this: